Critical Delay Factors in Construction Projects and Their Proposed Solutions from the Perspective of Total Quality Management


Sherif Awad Mohamed Elsherbiny, Samir Abdel-Fattah Gad, Ahmed Mohamed Abdel Alim

Received Revised Accepted Published
17 Aug 2023 20 Nov 2023 27 Dec 2023 03 Feb 2024

Citation :

Sherif Awad Mohamed Elsherbiny, Samir Abdel-Fattah Gad, Ahmed Mohamed Abdel Alim, "Critical Delay Factors in Construction Projects and Their Proposed Solutions from the Perspective of Total Quality Management," International Journal of Engineering Trends and Technology (IJETT), vol. 72, no. 2, pp. 1-8, 2024. Crossref, https://doi.org/10.14445/22315381/IJETT-V72I2P101

Abstract

Construction frequently encounters delays, which are a prevalent challenge. Any point in time during the project’s development might see a delay, either on its own or in combination with others. This study identifies the main causes, their effects, and ways to reduce delays in a construction project. This study used a literature review, workshops with contractors, clients, consultants, and a questionnaire. It was concluded that poor contract documents, escalation in material prices, poor focus on customers, delay in releasing the payments by clients, disputes, and design errors are the major delay factors of construction projects.

Keywords

Saudi construction projects, Delay factors, Total Quality Management, Construction delay.

References

[1] Ayman H. Al-Momani, “Construction Delay: A Quantitative Analysis,” International Journal of Project Management, vol. 18, no. 1, pp. 51-59, 2000.
[CrossRef] [Google Scholar] [Publisher Link]
[2] Sadi A. Assaf, and Sadiq Al-Hejji, “Causes of Delay in Large Construction Projects,” International Journal of Project Management, vol. 24, no. 4, pp. 349-357, 2006.
[CrossRef] [Google Scholar] [Publisher Link]
[3] F. Chalabi, and D. Camp, “Causes of Delays and Overruns of Construction Projects in Developing Countries,” CIB Proceedings, W-65, vol. 2, pp. 723-734, 1984.
 [Google Scholar
[4] Hemanta Doloi et al., “Analysing Factors Affecting Delays in Indian Construction Projects,” International Journal of Project Management, vol. 30, no. 4, pp. 479-489, 2012.
[CrossRef] [Google Scholar] [Publisher Link]
[5] Joseph F. Hair, Multivariate Data Analysis, Kennesaw State University, 2009.
 [Google Scholar] [Publisher Link]
[6] Shahid Hussain et al., “Critical Delaying Factors: Public Sector Building Projects in Gilgit-Baltistan, Pakistan,” Buildings, vol. 8, no. 1, pp. 1-16, 2018.
[CrossRef] [Google Scholar] [Publisher Link]
[7] Mohamed M. Marzouk, and Tarek I. El-Rasas, “Analyzing Delay Causes in Egyptian Construction Projects,” Journal of Advanced Research, vol. 5, no. 1, pp. 49-55, 2014.
[CrossRef] [Google Scholar] [Publisher Link]
[8] Promoting Integration In Providing Municipal Services and Residential Products TO Saudi Cities, MOMRA, 2017. [Online]. Available: http://www.momra.gov.sa/
[9] Mohammadsoroush Tafazzoli, and Pramen P. Shrestha, “Investigating Causes of Delay in US Construction Projects,” 53rd ASC Annual International Conference, pp. 611-621, 2017.
 [Google Scholar] [Publisher Link]

Time: 0.0022 sec Memory: 56 KB
Current: 1.95 MB
Peak: 4 MB